The facade is three days behind on levels 5 to 7.
58%actual progress
72%planned to date
- Requisition 118, anchor steelnot suppliedSAP · purchasing
- Panels installed this week12 of 30Procore · site manager report
- Facade through L7FridayPrimavera · site schedule